Lemon Avenue / SR-60 Interchange

updated 02/03/2010

PROJECT DESCRIPTION
The cities of Diamond Bar and Industry, in cooperation with the California Department of Transportation District 7 (Department) and the Federal Highway Administration (FHWA), propose to construct a new interchange on State Route 60 (SR-60) at Lemon Avenue.  The proposed project would improve traffic operations by providing direct access to SR-60 from the surrounding areas.

SCHEDULE
 Begin Project Construction Summer 2012
Complete Project Construction  Winter 2014

UPDATES

  • Comment period ended February 2008.

RELATED DOCUMENTS

State Route 60 / Lemon Avenue Interchange Initial Study / Environmental Assessment Executive Summary (PARTIAL DOCUMENT, SEE BELOW FOR MORE INFORMATION).

COMPLETE DOCUMENTATION AVAILABLE VIA THE CAL TRANS WEBSITE. For more information, call Gary Iverson at 213.897.3818 or visit www.dot.ca.gov/dist07/resources/envdocs/.

ALTERNATIVES

Three build alternatives and a no build alternative are under consideration and will be evaluated in detail in the project environmental document.  The build alternatives are described below.  Figures of these alternatives are also provided.

Alternative 2:  Half Interchange.  Alternative 2 would construct a half interchange on SR-60 at Lemon Avenue, with a westbound (WB) on-ramp from Lemon Avenue and an eastbound (EB) off-ramp over Lemon Avenue to Golden Springs Drive.  The existing soundwall along EB SR-60 west of Lemon Avenue would be removed, and a new soundwall would be installed along the edge of pavement of the EB off-ramp under Alternative 2.

Alternative 3:  Partial Interchange.  Alternative 3 would construct a partial (three-legged) interchange, a WB on-ramp, and EB off-ramp from Lemon Avenue.  It would also permanently remove the existing WB off- and on-ramps at Brea Canyon Road.  An auxiliary lane from the proposed EB on-ramp to the connector to SB SR-57 would be constructed under this alternative.  The existing soundwall along EB SR-60 west of Lemon Avenue would be removed and a new soundwall would be installed along the edge of pavement of the EB off-ramp and of-ramp.

Alternative 4:  Full Interchange.  Alternative 4 would provide a full interchange at Lemon Avenue without removing the existing WB access from Brea Canyon Road.  Alternative 4 is similar to Alternative 3, except that it adds a two-lane collector road between Lemon Avenue and Brea Canyon Road.  The collector road would replace the existing WB on-ramp from Brea Canyon Road and run parallel to SR-60 on the north.  It would terminate at Lemon Avenue.

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Download Acrobat Reader Download WinZip Download Word Viewer Download Excel Viewer Download PowerPoint Viewer